Not much has happened this week except somehow we've got a new split in the bi-fold doors...
And while the walls haven't been painted, the ceiling has.
Our bathrooms and tiling looks like it has been started.
Holes in the walls have been cut for electrical powerpoints and data points.
So there we are for another week! Thanks Syd and Andy for coming to visit :)
Site Start Date: Sept 3 2012
Slab Complete: Sept 15 2012 Frame Complete: Oct 4 2012
Lock Up Complete: Oct 18 2012